Project Description

  • The existing Erbil-Shaglawa-Mama-Jalka-Rewanduz-Hacıomran Highway, extending North-East from the Capital city Erbil to Iranian border is one of the important routes of Kurdistan to Iran.
  • The existing road carries considerable traffic, including heavy and long vehicles and need to be upgraded with alternate corridors to improve the horizontal and vertical geometry of the road.
  • It has been agreed by the Ministry of Construction and Housing to upgrade the existing route and constructing a new dual carriageway up to Hareer-Mama-Jalka interchange. And the final decision was made as to continue the route by a new design from the new Mama-Jalka interchange to Haciomran via Rewanduz and Jundian.
  • The scope of this study covers the works from the new Mama-Jalka Interchange up to Jundian.
  • This section applies to the execution of New Austrian Tunneling Method (NATM) in any type of rock. This section does not deal with specific topics of rock classification. Excavation may be carried out by drill and blast using pre-split or smooth blasting techniques or by road header or tunnel excavator. The New Austrian Tunneling Method (NATM) is based on the principle to take utmost advantage of the rock`s capacity to support itself, by careful measures and deliberate guidance of the forces during the readjustment process from the primary to the secondary state of stress, which takes place in the surrounding of the excavation. By this way, local progressive loosening will be limited by careful excavation methods and timely installation of the support elements and the rock mass will be able to support itself. The supports elements are shotcrete, wiremesh, rock bolts and steel ribs.

     Project Details

  • The project consists of 3 tunnels and 4 viaducts.
  • Preliminary design preparation for (Mamajalka Interchange / Hareer – Rawandoz – Jundian) Highway with Required Tunnels & Bridges and for all structures and installations (such as tunnels, viaducts, bridges, interchanges and installations for the maintenance and services) on the highway.
  • Detail designs of (Mamajalka Interchange / Hareer – R0wandoz – Jundian) Highway With Required Tunnels & Bridges
  • Bill of Quantities, Conditions of Contract of Technical Specifications required for the Construction contracts of the whole section.
  • Design Length of TunnelTunnel #1: 3600 m, Tunnel #2:  6860 m, Tunnel #3: 1750 m
  • Tunnel Height : 5,50 meter
  • Tunnel Tube Internal Area : 71 m2
  • Tunnel Circumference : 33 meter
  • Max. Avg. Wind Velocity: 9 m/sn.
  • Passenger Car Traffic Density : 800 vehicle/hour
  • Heavy Vehicle Traffic Density : 1200 vehicle/hour
  • Road Width Inside Tunnel Tube: 8.50 meters (2 lanes)
  • Tunnel Horizontal and Vertical Geometry Design Speed : 120 km/hr
  • Allowable Speed In Tunnel : 80 km/hr
  • Tunnel Excavation Method : New Austrian Tunneling Method
  • Number of Emergency Vehicle Exit : Tunnel #1: 3, Tunnel #2: 6, Tunnel #3: 2
  • Number of Emergency Pedestrain Exit : Tunnel #1: 2, Tunnel #2: 4, Tunnel #3: 1

Fire Extinguishing System:

All the fire suppression systems shall be designed to the highly reliable, having low operation and maintenance costs, operable with few numbers of personnel and as automatic as possible.

Ventilation System: Tunnel #1: 28, Tunnel #2: 64, Tunnel #3: 16 number of jet fans are used in ventilation design.

Jet Fan Properties

  • Flow (m3/s) : 26.3
  • Velocity (m/s) : 33.5
  • Thrust : 1004
  • Power (kw) : 30

Tunnel Electrical System:

Tunnel Electrical System Design consists of Tunnel Electrification and Lighting, Tunnel Emergency Announce System, Tunnel Emergency Call (Telephone) System, Signalization System, Tunnel controlling System.

57143276c59ee
571432a4c5bf1

Project Description

Railway line crosses Erbil- Altun Kopri Road at station Km 21+985. In the content of the rehabilitation of the road project, a railway underpass is planned at this location. A reinforced concrete box frame structure which provides 12.0m clear Width and 6,5 m vertical clearance above top of rail is designed for double track Railway line. The underpass is approximately 58 degree skew and 60 m long.

Services Provided

  • Prepare the alignment alternatives
  • Preliminary and Final Design
5714323e462d9
5714323e46834

Project Description

In the content of the Manisa – Menemen railway project, bridges are designed (3 reinforced pre-fabric truss which provide 16.0m clear width, 8 reinforced concrete box frame structure which provides 9.0 m clear width and 3 portal frames which provide 9.0m clear width). It is prepared 1/1000 scale maps with the route drawn of these maps, 1/1000 scale geological maps, expropriation plans and bill of quantities.

Services Provided

  • Preparation of Detailed Design
  • Geotechnical Survey
  • Soil Investigation
  • Preparation of Bill of Quantities
571431010ea1a
571431010efcf

Project Description

Taking into consideration high volume of traffic on the existing road, the Ministry of Construction and Housing has decided to initiate a new corridor study and then design and construction of new road.

BOTEK is given the assignment, which includes the corridor study of various alignments and selection and recommendation of the best suitable alignment to the Ministry and after the approval of the selected alignment, preparation of Preliminary and Final Design and also Tender Documents of new Erbil Koya highway.

The project starts after Kasnazan on Erbil – Koya Highway just after the dual carriageway ends. The project section is approximately 65 km and existing Koya – Suleymaniye road after Koya city.

Total length of the alignment is 59 km and has 1 major bridge, 67 culverts and 3 intersections. Design speed adopted is 120 km/hr, minimum horizontal curvature adopted on the alignment is R= 1000 m, maximum longitudinal grade is 6% which is used once in a critical location. This slope can be decreased after the detail survey. The road will be dual carriageway 2*2 with a 7 m median and 3.75 lane widths.

Services Provided

  • Prepare the alignment alternatives
  • Preparation of preliminary and detailed design
5713f772ec65a

Project Description

Preliminary and Final Design of 29 kilometer (2X3) State Motorway.

  • 29 Km Final Project
  • 29 Km Geotechnical Investigation Engineering Work
  • No. 12 (25600 m2) Bridge Projects Works
  • 29 Km Traffic Project Works

Services Provided

  • Horizontal and Vertical Alignment Studies
  • Preliminary and Final Design
  • Detailed Bridge Design
  • Drainage Design
  • Geological Studies
  • Hydrogeological Studies
  • Geotechnical Studies
5d135bbba3a41
5713f6df8b6cc

Project Description

Preliminary and Final Design of 34km State Roadway, (2×2)

A: 33,44km. Road construction project

B: 33,44km. Ground research engineering services construction

C: 33,44km. Traffic project construction

D: 5 piece (4966 m2) Services on Bridge Construction

Services Provided

  • Preliminary and Final Design
  • Detailed Bridge Design
  • Interchange Design
  • Drainage Design
  • Geological Studies
  • Hydrogeological Studies
  • Geotechnical Studies
Batinah Package 5 (1)
Batinah Package 5 (6)
Batinah Package 6 (1)

Project Description:
Design and Supervision of Batinah Expressway Package 5 and 6 has 86 Km to be built and 46 km link roads to be upgraded and dualized. Starts from the end of Muscat expressway. The alignment runs rearly parallel to the existing Batinah dual carriageway at a distance varying between 5 km and 20 km approximately on the mountain side, and ends near the Oman – UAE border at Khatmat Malaha.

Project Details:
2×4 Lanes Expressway(86 km) and 2×2 Lanes(46 km) width : 3,75 Polymer Modified Bitumen(PMB)
7 Interchanges(total 540 m) – Directional bridges(total 507.2 m),
7 River Bridges and Railway Bridge(1 Bridge 657.5m, 1 Bridge 492.5m, 1 Bridge 228.5m, 1 Bridge 360.5m, 1
Bridge 195.5m, 1 Bridge 228.5m, 1 Bridge 261.5m)
3 flyovers(total 180 m) and 6 underpasses(total 261.6 m),
Culverts, retaining and flood protection/training works
Toll plazas including operating systems for the revenue collection
Park Areas, Rest Areas and Service Areas

Sultanate of Oman Standard Documents for Building and Civil Engineering Works (both the third edition 1981 and the fourth edition 1999 are widely used) with risk allocation broadly following that of the FIDIC Red Book (Employer designs; contractor builds) all the works necessary for the construction and operation of the expressway.Link Roads.

Services Provided:

Design
Pre-Feasibility/Feasibility Studies Route Alignment Selection
Aerial Mapping
Geological and Geotechnical Investigations
Preliminary and Detailed Design of Expressway and Link Roads
Architectural and Design of Toll Plazas, Rest Areas and Service Areas
Preparation of Cost Analysis
Preparation Tender Documents and Specifications
Preparation of Environmental/Social Impact Assessment Report

Project Management
Tender Evaluation Report and help client during the selection of the Contractor
Prepare the project schedule with Primavera
Procurement approval
Schedule, attend and lead meetings with contractors
Hosting meetings with the Client, Authorities and with Contractor
Project documentation
Identify Possible trouble spots before becoming a claim from the contractor
Assess and evaluate Contractor Claims

Construction Supervision
Supervision of Motorway Construction
Supervision of Viaduct, Bridges
Supervision of Pavement and Earthworks
Supervision of Rest Area, Service Area, Toll Plazas and Toll Area Construction
Supervision of all Utility Lines Installations
Supervision of Relocation of Electric Lines and Gas Lines
Supervision of Lighting Works, Landscape Studies and Planning
Quality Assurance and Quality Control
Environmental management plan
Apply Health and Safety Requirement on Site
Preparation of Final Accounts and Payment Certificates

57143489dba3a
57143489dbfc7

Project Description

The platform width of Kırklareli–Dereköy–Aziziye Turkish – Bulgarian State Road Project is 10 m and pavement is only 7 m with surface treatment, after the completion of the proposed project platform width will be 12-14 m, the pavement will be 10 meter, and surface type will be asphalted concrete. By widening the existing platform width from 10 meter to 14 meter throughout Kırklareli–Dereköy–Aziziye the works consist of .A-Earth Works: Preparation for filling, cut excavation, Filled section works. B-Hydraulic Structure: Construction of 5 box culverts, 12 arc culverts, different types of retaining walls and drainage structures. C-Pavement Works: Crushed stone sub base (20 cm), Plant-mix base (15 cm), Bituminous hot mix base layer (8 cm), Asphalted concrete binder layer (6 cm), Asphalted concrete wearing layer (5 cm)