Project Description

Taking into consideration high volume of traffic on the existing road, the Ministry of Construction and Housing has decided to initiate a new corridor study and then design and construction of new road.

BOTEK is given the assignment, which includes the corridor study of various alignments and selection and recommendation of the best suitable alignment to the Ministry and after the approval of the selected alignment, preparation of Preliminary and Final Design and also Tender Documents of new Erbil Koya highway.

The project starts after Kasnazan on Erbil – Koya Highway just after the dual carriageway ends. The project section is approximately 65 km and existing Koya – Suleymaniye road after Koya city.

Total length of the alignment is 59 km and has 1 major bridge, 67 culverts and 3 intersections. Design speed adopted is 120 km/hr, minimum horizontal curvature adopted on the alignment is R= 1000 m, maximum longitudinal grade is 6% which is used once in a critical location. This slope can be decreased after the detail survey. The road will be dual carriageway 2*2 with a 7 m median and 3.75 lane widths.

Services Provided

  • Prepare the alignment alternatives
  • Preparation of preliminary and detailed design
5713f772ec65a

Project Description

Preliminary and Final Design of 29 kilometer (2X3) State Motorway.

  • 29 Km Final Project
  • 29 Km Geotechnical Investigation Engineering Work
  • No. 12 (25600 m2) Bridge Projects Works
  • 29 Km Traffic Project Works

Services Provided

  • Horizontal and Vertical Alignment Studies
  • Preliminary and Final Design
  • Detailed Bridge Design
  • Drainage Design
  • Geological Studies
  • Hydrogeological Studies
  • Geotechnical Studies
5d135bbba3a41
5713f6df8b6cc

Project Description

Preliminary and Final Design of 34km State Roadway, (2×2)

A: 33,44km. Road construction project

B: 33,44km. Ground research engineering services construction

C: 33,44km. Traffic project construction

D: 5 piece (4966 m2) Services on Bridge Construction

Services Provided

  • Preliminary and Final Design
  • Detailed Bridge Design
  • Interchange Design
  • Drainage Design
  • Geological Studies
  • Hydrogeological Studies
  • Geotechnical Studies
Batinah Package 5 (1)
Batinah Package 5 (6)
Batinah Package 6 (1)

Project Description:
Design and Supervision of Batinah Expressway Package 5 and 6 has 86 Km to be built and 46 km link roads to be upgraded and dualized. Starts from the end of Muscat expressway. The alignment runs rearly parallel to the existing Batinah dual carriageway at a distance varying between 5 km and 20 km approximately on the mountain side, and ends near the Oman – UAE border at Khatmat Malaha.

Project Details:
2×4 Lanes Expressway(86 km) and 2×2 Lanes(46 km) width : 3,75 Polymer Modified Bitumen(PMB)
7 Interchanges(total 540 m) – Directional bridges(total 507.2 m),
7 River Bridges and Railway Bridge(1 Bridge 657.5m, 1 Bridge 492.5m, 1 Bridge 228.5m, 1 Bridge 360.5m, 1
Bridge 195.5m, 1 Bridge 228.5m, 1 Bridge 261.5m)
3 flyovers(total 180 m) and 6 underpasses(total 261.6 m),
Culverts, retaining and flood protection/training works
Toll plazas including operating systems for the revenue collection
Park Areas, Rest Areas and Service Areas

Sultanate of Oman Standard Documents for Building and Civil Engineering Works (both the third edition 1981 and the fourth edition 1999 are widely used) with risk allocation broadly following that of the FIDIC Red Book (Employer designs; contractor builds) all the works necessary for the construction and operation of the expressway.Link Roads.

Services Provided:

Design
Pre-Feasibility/Feasibility Studies Route Alignment Selection
Aerial Mapping
Geological and Geotechnical Investigations
Preliminary and Detailed Design of Expressway and Link Roads
Architectural and Design of Toll Plazas, Rest Areas and Service Areas
Preparation of Cost Analysis
Preparation Tender Documents and Specifications
Preparation of Environmental/Social Impact Assessment Report

Project Management
Tender Evaluation Report and help client during the selection of the Contractor
Prepare the project schedule with Primavera
Procurement approval
Schedule, attend and lead meetings with contractors
Hosting meetings with the Client, Authorities and with Contractor
Project documentation
Identify Possible trouble spots before becoming a claim from the contractor
Assess and evaluate Contractor Claims

Construction Supervision
Supervision of Motorway Construction
Supervision of Viaduct, Bridges
Supervision of Pavement and Earthworks
Supervision of Rest Area, Service Area, Toll Plazas and Toll Area Construction
Supervision of all Utility Lines Installations
Supervision of Relocation of Electric Lines and Gas Lines
Supervision of Lighting Works, Landscape Studies and Planning
Quality Assurance and Quality Control
Environmental management plan
Apply Health and Safety Requirement on Site
Preparation of Final Accounts and Payment Certificates

57143489dba3a
57143489dbfc7

Project Description

The platform width of Kırklareli–Dereköy–Aziziye Turkish – Bulgarian State Road Project is 10 m and pavement is only 7 m with surface treatment, after the completion of the proposed project platform width will be 12-14 m, the pavement will be 10 meter, and surface type will be asphalted concrete. By widening the existing platform width from 10 meter to 14 meter throughout Kırklareli–Dereköy–Aziziye the works consist of .A-Earth Works: Preparation for filling, cut excavation, Filled section works. B-Hydraulic Structure: Construction of 5 box culverts, 12 arc culverts, different types of retaining walls and drainage structures. C-Pavement Works: Crushed stone sub base (20 cm), Plant-mix base (15 cm), Bituminous hot mix base layer (8 cm), Asphalted concrete binder layer (6 cm), Asphalted concrete wearing layer (5 cm)

57143444ea47a
worldbank_logo

Project Description

The Government of Georgia has received a grant from the International Development Association (IDA) for a Georgian infra-structure pre-investment facility (IPF). The purpose was  for as detailed engineering design and preparation of  bidding document based on World Bank standards for the 24km section of the E-60 Highway (this section) was between km56 and km80 (Iogeti-Sveniti). The section is located about 56 km. west from Tbilisi and is to be upgraded from a 2 lane to a 4 lane road

Services Provided

  • Revision/Completion of the preliminary design
  • Preparation of detailed design
  • Preparation of the bidding documents
  • Preparation of draft pre-qualification document (PQD)
  • Work plan and time schedule
  • Monthly progress reports
  • Technical reports (geometrical design, pavement design, bridge and structure design, bill of quantity, cost estimate),
  • Draft bidding documents
  • Final bidding documents
5714340553f8e

Project Description

In the content of the TEKIRDAĞ – MURATLI – BÜYÜK KARIŞTIRAN RAILWAY project, 1/25000 scaled track survey and Forest Management Map, 1/2000 scaled Strip Map Preparation and tracing the track into those maps, Preparation of expropriation Plans, Making the Required Drillings and other Soil Survey Works over the track, Making Projects of Engineering Structures like; Tunnels, Bridges, Retaining Walls and Subway Station Facilities and Railway according to the Technical Provision Principles, Superstructure, Making Projects of Electrification, Signalization, and Telecommunications, Preparation of EIA report, Feasibility Study of the track and reconnaissance and bill of quantities of track and tender documentation preparation  of  double lined Tekirdag-Murali-Buyuk Karistiran Railway Line having general standards maximum slope  %012,5 and minimum Radius curve of 3000m. (in obligatory places with the approval of the Client it can be changed.)

Services Provided

  • Prepare the alignment alternatives
  • Preparation of detailed Design
  • Geotechnical Survey
571433bd83cf3

Project Description

The work done to comply with the agreement and it’s annexes,  geological and geotechnical survey studies of bridges and culverts present in various kilometers was prepared, construction design and static-reinforced concrete calculations of  bridges and culverts was prepared, the profile and plans belonging to the aforesaid railway track was delivered to the Client, the geotechnical reports of the railway track prepared and delivered and the delivered documents, calculations, reports and projects are compliance with  the contract and specifications.

Services Provided

  • Prepare the alignment alternatives
  • Preparation of detailed drainage design
  • Preparation of detailed structures design
  • Preparation of detailed stations

Project Description

This project consists of detailed design for Galeri Street Hekimsuyu Street Intersection, Road and Intersection.

Scope of the Project

  • Design of road structures
  • Geotechnical Survey, Soil Investigation
  • Field Surveys
  • Drainage Design
  • Earthworks Calculations, Bruckner Calculations, Cross Sections
  • Bridge Design
  • Intersection Design
  • Bill of Quantities

Services Provided

  • Review of Control Drawings
  • Provision of Route Study
  • Identification and Assessment
  • Provision of Preliminary Design
  • Provision of Final Design
  • Provision of Supplementary Drawings
  • Data Processing and Documentation