HomeCategory

Motorways & Highways

AllBridges & TunnelsBuildings & FacilitiesMotorways & HighwaysRail Systems
t
ü
i

This Project is executed according to the FIDIC (MDBs) Harmonized Edition 2010. Funded by Saudi Fund for Development (SFD)

Project Description

The Ministry of Infrastructure plans to continue widening of the M2 national road, Pristina-Mitrovica, the project is designed to expand the M2 national road, from the Lum i Madh to the exit of Vushtrri. In this Consulting Service, is required to review, design and construction supervision of National Road M2: segment Lumi Madh – Vushtrri – Mitrovica. The beginning of the track is at Lumi Madh village and the end of the track will be at the entrance to Mitrovica (L=20km), the final points will be assigned by the Ministry of Infrastructure.  Task 1 – Detailed Engineering Design (the section from 21.50km to 26.7km); Task 2 – Review of Existing Detail Design Documents (the section from 7.165km to 16.95km); Task 3 – Preparation of Technical Specification and Bidding Documents including selection, evaluation and recommendation on the qualified contractors for both sections Task 4 – Supervision of Works and Contract management along with IPC certification and approvals for both sections.

Services Provided

BOTEK will perform in following Task:

  • Preparation the Detailed Engineering Design (the section from 21.50km to 26.7km);
  • Review of Existing Detail Design (the section from 7.165km to 16.95km);
  • Assistances in Preparation of Technical Specification and Bidding Documents, evaluation and recommendation on the qualified contractors;
  • Supervision of Works and Contract management along with IPC certification and approvals (the section from 7.165km to 16.95km and section from 21.50km to 26.7km).
ğ
1
c

Project Description

Projects consist of Consultancy Services design review and construction supervision of road works (20.3km) including two fly overs and bus stations along the road.

Services provided; Review the design to ensure technical soundness prior to implementation of the works. Carry out Supervision of Works to ensure compliance with the approved design, drawings, specifications, conditions of contract and sound engineering practice. Review of the proposed traffic deviations during construction to ensure that the proposed traffic arrangement results in minimal disruption. Carry out supervision of activities during the defect liability period.

The duration of the assignment is 46 months with 248 staff months.  Construction work cost is US$ 200 million.

The contract is standard United Republic of Tanzania Government procurement contract in accordance with AfDb rules and procedures for the use of consultants. The Construction Supervision is in accordance with the FIDIC conditions of contract.

Technical Category of the road is: State Roads in an urban area.


Services Provided

  • Design review and detailed design activities are carried out to the appropriate technical standards;
  • Traffic Studies
  • Supervision services for widening, reconstruction, rehabilitation and construction
  • Determination of horizontal and vertical alignment and preparation of the reports
  • Hydrological and Hydraulic Surveys
  • Interchange Design
  • Hydraulic culvert and underpass designs
  • Drawings and preparation of final report
  • Drainage Works
  • Bill of Quantities
  • Landscape Design
a

Project Description

It covers Survey and Project Consultancy Services of 19 Km Road.

  • 19.1 Km Final Project
  • 19.1 Km. Traffic Project
  • 19.1km Drainage Project
  • 19.1 Km. Geotechnical Research Engineering Services
  • 5   Interchange Project
  • 6   Viaduct Project (51661 m2)
  • 1  Close-Open Structure Project(145m)
  • 4   Bridge Project(15413 M2)
  • 1  2x(L2x6)Underpass Project (41  M)
  • 12  Bridge Geotechnical Report
  • 4    Double Tube Tunnel (4300,3 m
yol
way
highway

Project Description:

The project includes preliminary and final design services for Alanya – Gazıpaşa separation and Taşkent – Başyayla separation road. 21.8km Surveying and Project Enginerring Services. 21.8km (433.50 Ha) 1/1000 Scale Mapping, 4 Viaduct (7167.63 m2), 1 Bridge Project (1257,42m2), 6 Single Tube Tunnel Project (8998,80m)

Category of the specific road section:  2×1 State Road.

Services Provided

  • Corridor Survey
  • Mapping Works
  • Determination of horizontal and vertical alignment and preparation of the reports
  • Hydrological and Hydraulic Surveys
  • Bridge and Interchange Design
  • Hydraulic culvert and underpass designs
  • Drawings and preparation of final report
  • Drainage Works
  • Bill of Quantities
  • Traffic Studies
  • Landscape Design
j
a

Project Description:

The project includes preliminary and final design services for 48km road.

Services Provided

  • Corridor Survey
  • Mapping Works
  • Determination of horizontal and vertical alignment and preparation of the reports
  • Hydrological and Hydraulic Surveys
  • Bridge and Interchange Design
  • Hydraulic culvert and underpass designs
  • Drawings and preparation of final report
  • Drainage Works
  • Bill of Quantities
  • Traffic Studies
  • Landscape Design
b
c
isdb

This Project is executed according to the FIDIC Condition of Contract Funded by Islamic Development Bank (IsDB)

Project Description

This project is located in the islands of Java (in provinces of Central Java and East Java) and Kalimantan (West Kalimantan and East Kalimantan).

Project scope consists of supervision services for Widening, Reconstruction, Rehabilitation and Construction of 77km of National, Provincial and Kabupaten Roads, Bridges and associated Drainage Structures. This is an ISDB financed project.

Services Provided

  • Design review and detailed design activities are carried out to the appropriate technical standards
  • Supervision services for widening, reconstruction, rehabilitation and construction
  • Supervision guidance and organization of constructions supervision teams
  • Establish and monitor construction quality assurance
  • Monitoring of construction schedules comparing actual progress to planned
  • Monitoring of costs and recommendation for approval of payments to contractors
  • Support the Field Team, in supervision of the setting-up, organization and lay out of the Contractor’s field laboratory and in monitoring the mobilization of the equipment
  • Monthly Payment Certificates
a

Project Description

Projects consists of Consultancy Services for Preliminary and Final Design of 240km Motorway

Services Provided

  • Corridor Survey
  • Mapping Works
  • Determination of Horizontal and Vertical Alignment and Preparation of the Reports
  • Hydrological and Hydraulic Surveys
  • Bridge and Interchange Design
  • Hydraulic Culvert and Underpass Designs
  • Drawings and preparation of Final Report
  • Drainage Works
  • Bill of Quantities
  • Traffic Studies
  • Landscape Design
5f9060f045b57
5f90613851aa1
5f9060a699a0f

Project Description

Project includes Construction Supervision and Consultancy Services for Tokat – Niksar / Turkey Road Km: 0+000 – 48+962. Tokat – Niksar Road is an important arterial road for E80 State Road which provides link between Sivas, Tokat cities and Amasya – Erzincan cities and E70 State Road which connects Samsun and Ordu cities. Moreover, Tokat – Niksar Road includes 8 Bridges which have a total length of 582 m and 18 interchanges.

Services Provided

  • Supervision of Road Construction
  • Supervision of Bridge & Structure Constructions
  • Supervision of Interchanges Constructions
  • Line Installations and Lighting Works
  • Traffic Signs and Signalization
  • Drainage Works
  • Landscape Studies and Planning
  • Quality Control
  • Data Processing and Documentation
  • Preparation of Final Accounts and Payment Certificates
5713ee8f428ad
b

Project Description:

Project consists of Design Review and Construction Supervision Works for 13km section of Batel – Gali – Zakho Road and Design Supervision of Batel and Smail Ava Interchanges in Duhok.

Services Provided

1. Design Review

  • Data Collection and Site Reconnaissance
  • Traffic Study
  • Geometric Design
  • Field Surveys / Topographic Surveys
  • Geotechnical Study / Surveys
  • Hydrological Surveys
  • Structural Concept Design
  • Drainage Concept Design

2. Construction Supervision

  • Ensuring that the notice to commence the works is issued in accordance with contract requirements
  • Supervision of Contractor’s work method, temporary/perminent works, drawings, quality control system etc.
  • Site security and safety, traffic management, health and safety and environmental protection
  • Verification of as-built drawings
  • Approval of drawings for 2 interchanges
c

Project Description

Yusufeli Dam and Hydroelectric Power Plant is located on Coruh River, about 40 km southwest of Artvin City center and about 10 km downstream of Yusufeli Town. It is the highest dam of Turkey and 6th highest dam of Europe.  Yusufeli Dam Access Roads is located alongside the Coruh River. The project consists of survey and project consultancy services for Yusufeli Dam Access Roads including technical studies, preliminary and final design.  Yusufeli Dam Access Road will provide continuous accessibility between Erzurum, Ardahan, Kars provinces and Yusufeli district.

Project Details

  • 7 Bridges
  • 1 Special Bridge
  • 3 Viaducts ( The longest viaduct has a length of 600 m and height of 160 m)
  • 47 Tunnels (Total Length of tunnels: 35 km; The longest tunnel’s length is 3200 m)

Total Length of the roads: 70 km

Services Provided

  • Topographical Surveys
  • Road Structures (Bridge, viaduct etc.)
  • Horizontal-Vertical Alignment Studies
  • Hydraulic Surveys
  • Interchange projects
  • Tunnel Project Services
  • Drainage Works
  • Cross-section and Clearence Drawings, Bruckner
  • Traffic Studies
  • Environmental Impact Assessment